Follow

OnDemand Implementation Plan & Timeline

Summary 

Below is a outline and timeline of the basic OnDemand implementation.

 

----------- Implementation Plan ------------

STEP 1:

Initial Configuration

Project kick-off and setting foundation for company database with initial data.

STEP 2:

Core Configuration

Configuration of production processes, master data, recipes, …

STEP 3:

Web-based Training

Learning environment (test database) will be provided for three weeks of scheduled group training webinars.

and week of group training webinars. This virtual training phase is crucial for success in Go-Live phase.

STEP 4:

Go-Live Preparation and Testing

New database will be tested by running through series of day-to-day processes.

STEP 5:

Go-Live Transition

Opening balances will be captured at this step.

Assistance with inputting transactional records.

---------- Implementation Timeline -----------

  Monday Tuesday Wednesday Thursday Friday
WEEK 0    

Project kick-off

 

Core

tabs due

WEEK 1 Yellow tabs due       Blue tabs due
WEEK 2    

Recipe creation

sheets due

   
WEEK 3

---------------------------- Webinar training -----------------------------------

WEEK 4

---------------------------- Webinar training -----------------------------------

WEEK 5

---------------------------- Webinar training -----------------------------------

WEEK 6

----------------------------- Prep & Test Week ---------------------------------

WEEK 7

---------- Go-Live Week / Opening Balances Captured ------------

 

 

*Orchestra Software’s OnDemand implementation requires 8 weeks from Kick-off to Go-Live

 