BoM Trace

Report Summary

Printed Report Title:   BOM Consumed Items Trace

For a given produced item, this report will show all of the components used to make it and the cost for each.

 

Default Location In Orchestrated

Base Module: Production > Production Reports > Orchestrated Reports

Reports Module: Reports > Production > Orchestrated Reports

*These are the standard default locations. Your locations may be different.

 

Typically Used by

Production Managers and Planners would review that all the correct components and quantities are on a given Bill of Materials

Key Requirements

none

Parameter Entry Options

Required:

Select Item to Trace 
Enter Qty to produce (in multiples of the standard BOM quantity)

 

Optional:

Last Price Paid (Blank) or Choose Price list

Parameter Entry Image

 

Report Sample Image

 

 

 

Version 4.5.1.0

 